Ball mill during operation needs the operation? The use of the ball mill is a problem how to do? How to solve? Here Xiaobian to explain in detail.
The first is the ball mill operation processes, operational procedures in accordance with the priority order.
1 car prior to the mechanical and electrical parts, check the connecting bolts are loose; the lubrication points, lubrication is normal, normal gear and reliable protection device intact, electrical instruments, sensitive, motor carbon brush.
2, turning a week, the rotating part of the inspection equipment around with or without obstacles, and eliminated. Allowed to stand around in startup.
3 After the check, press the start button to start the motor, pay attention to current changes. Mill equipment no more than two consecutive start, the first and second separated for more than five minutes, the third starter, must be the same electrical fitter with the check, before starting. Shall not start the same since, to be interleaved with other devices in order to avoid tripping.
4, the normal operation of the mill should be strictly in accordance with water supply, to the mine, adding the provisions of the ball, ban overloaded, idle time is not more than 15 minutes, and avoid to damage the liner.
5, the operation should pay attention to check whether the cylinder leakage pulp, carefully observe the current, voltage, feed, water supply is normal, every half hour to check motor and spindle temperature is not greater than 60. С, identify problems in time | shaker .
6, the operation to observe the hollow shaft, the oil ring is rotating with oil, the hollow shaft temperature is normal, such as found hollow shaft fever, close to bush-burning, they should take immediate measures to forced cooling may not stop immediately in order to avoid axle . " At the same time careful to check each lubrication oil temperature, regular refueling.
7 mill parking should be preceded by stop to the mining, concentrate has been dealt with in standby, stop the water supply. Press the stop button, pull down the gates.
8, without notice, blackout, the first pull down the knife, press the stop button to stop to the mining, water supply.
9, parking, clean-up of mineral processing equipment and sanitation, to ensure civilized production.
http://www.findxk.com/jbt.htm mixing drum
http://www.findxk.com/gts.htm drum screen
palabras clave: Ball mill, ball mill equipment, processing equipment, a double,
Usted es el 13477 visitante
derechos de autor © GuangDong ICP No. 10089450, Henan Hongxing Mining Machinery Co., Ltd. Todos los Derechos Reservados.
apoyo técnico: Shenzhen Allways tecnología desarrollo Co., Ltd.
AllSources red'sDescargo de responsabilidad: La legitimidad de la información de la empresa no asume ninguna responsabilidad de garantía